ADVISORY CIRCULAR
SUBJECT
INSTRUMENT FLIGHT PROCEDURE (IFP) SPONSOR AND PROCESS FOR SUBMISSION OF IFPs FOR APPROVAL
DATE 15 May 2026
AC NUMBER AC 172.04
VERSION 1.0
NOTE: THIS ADVISORY CIRCULAR IS PUBLISHED TO PROVIDE REGULATORY INFORMATION AND DESCRIBE ACCEPTABLE MEANS OF COMPLIANCE WITH
THE GENERAL AUTHORITY OF CIVIL AVIATION REGULATIONS (GACAR).
CHAPTER 1 – BACKGROUND
1.1 Purpose.
This Advisory Circular (AC) provides regulatory guidance and describes the process applicable to Instrument Flight Procedure (IFP) Sponsors in relation to IFP design activities and defines the formal process for submission, withdrawal, and approval of IFPs by the GACA President in accordance with GACAR Part 172.
This AC further provides procedural guidance to ensure:
- Clear delineation of responsibilities between the IFP Sponsor and the IFP Custodian; - Effective regulatory oversight and control prior to IFP approval and promulgation; - Compliance with safety, aeronautical data integrity, and IFP process management
requirements.
1.2 Applicability.
This AC applies to:
- Instrument Flight Procedure Design Service Provider (IFPDSPs) acting as IFP Custodian;
- Air Navigation Service Provider (ANSP) certificated under GACAR Part 171 acting as IFP Sponsor;
- Aerodrome or heliport operator acting as IFP Sponsor; and - Flight Validation Service Providers (FVSPs), where applicable.
1.3 Cancellation.
This is the first official version of this AC, and it cancels no other ACs.
1.4 Related Regulatory Provisions.
This AC must be read in conjunction with the following:
- GACAR Parts 1, 4, 5, 97, 170, 172, 175, and 199.
AC 172.04
Page 1 UNCONTROLLED DOCUMENT WHEN DOWNLOADED
Consult the GACA website for current version
Version 1.0
- eBook Volume 8 - Air Navigation Services - Certification & Administration 1.5 Related Reading Material.
(a) Advisory Circulars AC172-01 and AC172-03; (b) ICAO Annexes 2, 4, 11 and 15; (c) ICAO PANS-OPS Procedures for Air Navigation Services – Aircraft Operations
(Doc 8168): (1) Volume I – Flight Procedures; and (2) Volume II – Construction of Visual and Instrument Flight Procedures (d) ICAO Quality Assurance Manual for Flight Procedure Design (Doc 9906): (1) Volume 1 – Flight Procedure Design Quality Assurance System; (2) Volume 2 – Flight Procedure Designer Training (Development of a Flight
Procedure Designer Training Programme) (3) Volume 3 – Flight Procedure Design Software Validation; (4) Volume 5 – Validation of Instrument Flight Procedures; and (5) Volume 6 – Flight Validation Pilot Training and Evaluation; (e) ICAO Manual on the Development of a Regulatory Framework for Instrument Flight Procedure Design Service (Doc 10068); 1.6 Definition of terms used in this AC. This AC does not introduce any new definitions. 1.7 Approval. This AC has been approved for publication by the Executive Vice President of Aviation Safety and Environmental Sustainability Sector of the GACA.
AC 172.04
Page 2 UNCONTROLLED DOCUMENT WHEN DOWNLOADED
Consult the GACA website for current version
Version 1.0
CHAPTER 2 - IFP SPONSOR
2.1. Definition of IFP Sponsor
In accordance with GACAR Part 172, §172.7, an IFP Sponsor is defined as the aerodrome or heliport operator, or the Air Navigation Service Provider (ANSP) certificated under GACAR Part 171.
IFP Sponsor may initiate the development or withdrawal of an Instrument Flight Procedure.
2.2 IFP Sponsor roles
As specified in GACAR Part 172, §172.7, the IFP Sponsor must:
1. Initiate IFP proposals based on validated operational needs;
2. Provide operational requirements and supporting information;
3. Provide validated aeronautical data as well as obstacle and terrain data;
4. Contract with a certificated Instrument Flight Procedure Design Service Provider (IFPDSP) serving as the IFP Custodian;
5. Ensure, through coordination with the IFP Custodian, that each approved IFP is subject to maintenance and periodic review in accordance with GACAR Part 172; and
6. Coordinate with IFP Custodian for publication activities in KSA AIP following regulatory approval.
The IFP Sponsor must not assume technical responsibilities for:
- IFP design; - IFP Design verification; - IFP ground and flight validations; - IFP maintenance and periodic review; and - Compliance declarations.
Technical accountability remains only with the IFP Custodian (IFPDSP).
2.3 Formal Arrangement between IFP Custodian and IFP Sponsor
The IFP custodian must establish and maintain a formal, documented agreement with the IFP Sponsor that clearly defines:
- Roles and responsibilities of each party; - Provision of aeronautical, obstacle and terrain data; - Safety assessment and risk management coordination; - Periodic review and IFP management processes; - Governance procedures for withdrawal of IFPs; - Regulatory submission and communication responsibilities.
AC 172.04
Page 3 UNCONTROLLED DOCUMENT WHEN DOWNLOADED
Consult the GACA website for current version
Version 1.0
2.4 IFP design pre-requisites
The following pre-requisites must be established to ensure an efficient and timely IFP design process:
- Up-to-date Aeronautical and Obstacle Data: The IFP Sponsor is responsible for ensuring that the contracted IFP Custodian (IFPDSP) is provided with current, validated aeronautical data, terrain data and obstacle survey data suitable for the intended procedure design. This must include updated aeronautical infrastructure data and surveyed coordinates for any new navigational aids installed.
- Project Planning and Timeline: A reasonable and realistic project timeline must be established, considering all external dependencies, including design activities, regulatory review, flight validation, chart production, and AIRAC promulgation cycles.
- Safety Risk Assessment: If required under GACAR Part 172 and ICAO Doc 8168 (PANS-OPS), the IFP Custodian must ensure that a Safety Risk Assessment (SRA) is conducted in coordination with the IFP Sponsor.
- Formal Notification: The IFP Sponsor must formally notify the GACA President once a decision has been made to initiate an IFP design project (development or withdrawal).
IFP RESPONSIBILITY MATRIX
Function
Initiate new IFP design
Request withdrawal of Published IFP
Approval withdrawal of Published IFP Data Provision IFP Design IFP Ground Validation IFP Flight Validation IFP Compliance Declaration IFP Periodic Review IFP maintenance
IFP Sponsor
✔ ✔ (operational reasons)
✔
IFP Custodian (IFPDSP)
FVSP
AIS service provider
GACA President
✔ (safety reasons)
Verify ✔ ✔ ✔ ✔ ✔ ✔
✔ (regulatory grounds)
✔
Oversight Oversight Oversight Oversight Oversight Oversight
AC 172.04
Page 4 UNCONTROLLED DOCUMENT WHEN DOWNLOADED
Consult the GACA website for current version
Version 1.0
Submission to GACA
✔
President to request IFP approval
(via
✔
Custodian)
IFP Regulatory Approval
Submission to AIS Provider ✔ for publication in KSA AIP
Submission to GACA
President to request IFP
publication acceptance
IFP Acceptance for
publication in KSA AIP
✔
✔ ✔
AC 172.04
Page 5 UNCONTROLLED DOCUMENT WHEN DOWNLOADED
Consult the GACA website for current version
Version 1.0
CHAPTER 3 – PROCESS FOR INTRODUCTION OF NEW IFP AND WITHDRAWAL OF PUBLISHED IFP
3.1 Instrument Flight Procedure Process
3.1.1 The instrument flight procedure process encompasses: - Initiation and collection of requirements and constraints; - Acquisition of data; - Flight Procedure Design (FPD); - Ground validation; - Flight validation; - Approval; and - Publication.
3.1.2. This process includes review, verification and validation processes which are necessary to minimize the possibility of errors. It considers the safety analysis necessary prior to implementation.
3.1.3 The process also incorporates the periodic review of data, criteria and feedback from operational implementation.
3.1.4 The process covers the entire lifespan of an IFP, from the initial development up to the withdrawal.
3.2 Development of new IFP The introduction of a new Instrument Flight Procedure (IFP) must follow a structured process to ensure compliance with GACAR Part 172.
The process for the development and approval of a new IFP normally includes the following stages:
3.2.1 Stage 1 – Initiation and collection of requirements and constraints
The IFP Sponsor should:
- Identify and document the operational need for the procedure; - Contract a certificated IFPDSP to serve as IFP Custodian; - Coordinate with the IFP Custodian to conduct a preliminary feasibility assessment; - Coordinate with the IFP Custodian to evaluate airspace and operational implications; - Participate in determining whether a Safety Risk Assessment (SRA) is required,
particularly where airspace structure or operational concepts are affected; and - Formally notify the GACA President of the IFP initiation.
AC 172.04
Page 6 UNCONTROLLED DOCUMENT WHEN DOWNLOADED
Consult the GACA website for current version
Version 1.0
3.2.2 Stage 2 – Data acquisition
The IFP Sponsor should provide the IFP Custodian at a minimum with:
- Aerodrome/heliport aeronautical data compliant with GACAR Part 139 or 138 (where applicable);
- Obstacle and terrain data meeting the integrity, accuracy, and resolution requirements of GACAR Part 175;
- Defined operational and performance requirements.
All data must be validated, traceable, and quality-controlled prior to commencement of design activities.
3.2.3 Stage 3 – IFP Design Development
The IFP Custodian must:
- Design the IFP in accordance with ICAO Doc 8168 (PANS-OPS), Volume II, and GACAR Part 172 requirements, including determination of applicable Visibility Minima;
- Apply quality assurance processes in accordance with ICAO Doc 9906 and the IFPDSP operation manual (FPDOM) & Quality Management System (QMS);
- Utilize validated Flight Procedure Design Automation Tools in accordance with GACAR §172.51;
- Produce a complete Design Package in accordance with GACAR §172.67 and Appendix C;
- Submit a formal Declaration of Compliance in accordance with GACAR §172.69.
3.2.4 Stage 4 – IFP Validation
The IFP Custodian must complete the validation package prior to submission to the GACA President for regulatory approval.
The validation package may include, but is not limited to, the following:
- Ground validation report; - Flight validation report (where required); - Navigation database validation evidence (where applicable); and - Safety risk assessment documentation (where applicable).
All validation activities must comply with the requirements of GACAR Part 172.
3.2.5 Stage 5 – Submission to the GACA President
- The IFP Custodian must submit the complete IFP Design Package to the GACA President for approval in accordance with GACAR Part 172, through official GACA channels (e-services, AJWAA platform, or formal correspondence, as applicable);
AC 172.04
Page 7 UNCONTROLLED DOCUMENT WHEN DOWNLOADED
Consult the GACA website for current version
Version 1.0
- The IFP approval review process is detailed in eBook Volume 8, Chapter 4, Section 4; - Incomplete or non-compliant submissions will not be processed.
3.2.6 Stage 6 – Regulatory Review
Upon receipt of the IFP design submission, GACA/ANS Aviation Safety Inspectors will conduct a regulatory review for formal IFP approval in accordance with eBook Volume 8, Chapter 4, Section 4. At a minimum, the review must include:
- Verification that the submission is made by a certificated IFPDSP; - Assessment of compliance with GACAR Part 172; - Verification of conformity with ICAO PANS-OPS design criteria; - Evaluation of the adequacy of validation activities; - Confirmation of aeronautical and obstacle data integrity; - Review of quality assurance documentation and traceability; and - Confirmation of overall regulatory compliance.
GACA/ANS Aviation Safety Inspector may request:
- Additional information or clarification; - Additional validation activities; and - Corrective actions to address identified deficiencies.
3.2.7 Stage 7 – IFP Approval